Case Studies
Case Studies
Restoration
New Build
Acorn Centre
Brammall Music Building
Church Farm
Crownhill Crematorium
De Montford University
Edinburgh Napier University
Flag Fen
Hampton Hargate Primary
Heathfield
Herbert Art Gallery
Herringswell Manor
Isle of Man
Kings Troop, Woolwich
Long Barn, Cockthorpe
National Museum of Wales
Newnham College
Nottingham Vets School
Palace Theatre, Redditch
Rapier Street
Rawmarsh Joint Services Centre
Risbygate Street, Bury St Edmunds
Selwyn College
Southwell School
The Arc
Vine Inter Church School
Woodgrange Road
Project Overview
Client: The NHS
Location: Oxmoor, Huntingdon
Architect: Macmon Chartered Architect
Contractor: Gleeson Building
Value: £600,000
Programme: 11 Month
Materials: 5,000m² Rheinzink Natural zinc, 1500m² Composite panels, 40,000m Softwood boarding

The CEL Group installed 5,000m2 of Rheinzink Natural zinc to the roof of the three-storey main building, complete with Rheinzink rainwater gutters and downpipes, vertical cladding to the main façade and feature windows.
Phase two consisted of composite insulated panels, 1100m zinc roof to the main building, vertical cladding and zinc rainwater goods, all visually in sympathy with the phase one work.